DYNEGY HOLDINGS: Subject to NYSDEC’s Permit Renewal for Roseton

Dynegy Holdings, Inc. continues to be subject to the New York State Department of Environmental Conservation’s (NYSDEC) Draft State Pollutant Discharge Elimination System (SPDES) Permit renewal, which was issued last April 2005, for the Roseton plant.

The permit is opposed by…

DYNEGY HOLDINGS: Subject to NPDES Permit for Moss Landing Plant

Dynegy Holdings, Inc. is subject to the California Regional Water Quality Control Board’s NPDES (National Pollutant Discharge Elimination System) permit (issued in 2000) for the Moss Landing power generating facility that did not require closed cycle cooling.

A local environmental group…

DYNEGY HOLDINGS: Inquiry on Projects at Danskammer Plant Ongoing

Dynegy Holdings, Inc. says the U.S. Environmental Protection Agency’s investigation regarding projects at the Danskammer power generation facility is ongoing.

In March 2009, the Company received an information request from the EPA regarding maintenance, repair and replacement projects undertaken between January…

DYNEGY HOLDINGS: Expended $225Mil in 2010 for Envt’l. Protection

Dynegy Holdings, Inc.’s aggregate expenditures (both capital and operating) for compliance with laws and regulations related to the protection of the environment were about US$225 million in 2010 compared to about US$320 million in 2009 and about US$245 million in…

DYNEGY INC: Awaits Ruling on Bids to Junk Greenhouse Gases Suit

Dynegy Inc. is awaiting ruling on the multiple motions to dismiss a case styled, Native Village of Kivalina and City of Kivalina v. ExxonMobil Corporation, et al.