DOW CHEMICAL: Has $140M Environmental Remediation Charge in 2008

The Dow Chemical Company says that amounts charged to income on a pretax basis related to environmental remediation totaled US$140 million in 2008, US$92 million in 2007 and US$125 million in 2006.

Capital expenditures for environmental protection were US$193 million in…

DOW CHEMICAL: Facing $354T Penalty on Alleged Emission in Texas

The Dow Chemical Company faces a total civil penalty of US$354,000 over alleged air emission events at its Freeport, Tex., site.

In Oct. 1, 2007, the Company received a Notice of Enforcement (NOE) from the Texas Commission on Environmental Quality (TCEQ)…

DOW CHEMICAL: $202,325 Settlement on Tex. Breaches Still Pending

The Dow Chemical Company says that a US$202,325 settlement over air regulations breaches at its Freeport, Tex., site is subject to final approval by the Texas Commission on Environmental Quality (TCEQ) Commissioners.

On various dates, the Company received Notices of Enforcement…

DOW CHEMICAL: Accrues $290M Liability for Remediation at Dec. 31

The Dow Chemical Company accrued a liability of US$290 million on the remediation of current or former Dow-owned sites at Dec. 31, 2008, compared with US$294 million at Dec. 31, 2007.

In addition to current and former Dow-owned sites, under the…

DOW CHEMICAL: Accrues $35Mil for Midland Site Cleanup at Dec. 31

The Dow Chemical Company had an accrual of US$35 million for environmental remediation and investigation association with its Midland, Mich., site at Dec. 31, 2008, compared with US$36 million at Dec. 31, 2007.

In 2008, the Company spent US$36 million (US$52…

DOW CHEMICAL: Facing $330,112 Fine on Alleged Breaches in Conn.

The Dow Chemical Company is facing environmental-related civil penalties in the amount of US$330,112 proposed by the U.S. Environmental Protection Agency Region 1 office for alleged violations in the Company’s Allyn’s Point, Conn., manufacturing facilities.

The Company received an Administrative Complaint…

DOW CHEMICAL: Accrues $25MM for Freeport Site Cleanup at Dec. 31

The Dow Chemical Company had an accrual of US$25 million related to environmental remediation at its Freeport, Tex., manufacturing site at Dec. 31, 2008, compared with US$37 million at Dec. 31, 2007.

In 2008, US$5 million (US$6 million in 2007) was…

DOW CHEMICAL: Accrues $18M for Off-Site Cleanup to a Mich. Site

The Dow Chemical Company, at Sept. 30, 2008, has an accrual of US$18 million for off-site corrective action to a manufacturing site in Michigan. This amount is included in the total accrued obligation of US$306 million at Sept. 30, 2008…

DOW CHEMICAL: Accrues $306M in Remediation and Restoration Costs

The Dow Chemical Company, at Sept. 30, 2008, had accrued obligations of US$306 million for environmental remediation and restoration costs, including US$23 million for the remediation of Superfund sites.

The Company’s accruals for environmental matters are recorded when it is probable…

US EPA: Certifies Completion of Uravan Superfund Site Cleanup

DENVER, Colorado — September 29, 2008 — A chapter in the history of the uranium industry in western Colorado closed when the U.S. Environmental Protection Agency (EPA) certified the completion of the 20-year cleanup of the Uravan Mill Superfund Site.…